In Spring 2012 the development is nearly finished, and will be known as Bedford Row, after Francis Bedford, the architect of the church in Trinity Church Square.


Perhaps easy enough to tell now, when Bedford Row looks new (and the lack of chimney stacks is a clue). But will it be so clear a few decades hence?
Denne Construction have been awarded a 72-week contract to build flats and house on this site. Contact them on 01795 434700. To download their first newsletter of December 2009, click here.
A few men have been around the north of the building site, playing loud radio music, repainting the fence and putting up some scaffolding, also some surveying and new spray painted marks on walls............. Obviously no one from the developers or Metro the demolition company had passed on the key to the barricaded street part of the site. The new builders secured the pavement by removing the padlocks and fixing the doors permanently shut. This meant no access to electricity or BT if any resident had problems. Luckily one of the builders was caught vaulting over the wall as they were about to leave. He informed me work would begin in earnest in February and as TNRA has a key to the removed padlocks he re-instated them and dropped the key back. So NB and TNRA still have access to the pavement utilities if you need this.
Work has finally started on the site. To download Denne Construction's second newsletter, click here. Any enquiries about the project should be addressed to the contracts manager, Patrick Leyden, on 01795 434700.
To download the third newsletter, click here.
Ali Walker writes:
The spring has arrived and with it the relentless growth upwards of the new homes at the centre of our estate. The building at the southern end has reached 1st floor level and again at the southern end, I am just about to lose the air and space and view I have had for 20 years.On the whole the building works under the management of Pat Layden are going well and Denne have been very responsive to the inevitable problems that have arisen. TNRA has helped to resolve the issues that have come up. The main problems have been: waiting cement lorries, rubbish collection hiccups in the back lane, and oversailing crane problems.
There are still annoying rubbish collection issues. Southwark Council at one moment removing all our bins. This is especially irritating as we spent a lot of time discussing this at the planning stage as TNRA predicted there would be problems.
The unpredictable one was the oversailing crane. Suddenly three houses in Merrick Square not only had a huge crane tower looming over them but the arm is not in use, so loose and swinging in the wind, it swings worryingly over their gardens. TNRA helped initially with getting Denne and the managing agents to take the problem seriously and we are pleased that eventually acceptable compensation has been awarded to the tenants from the developers.
April 2011
To download the fourth Denne newsletter, click here![]() December 2010 from 32 MS |
![]() January 2011 from 32 MS |
![]() February 2011 on site |
![]() February 2011 on site |
![]() February 2011 on site |
![]() February 2011 on site |
![]() February 2011 from 32 MS |
![]() March 2011 from 34 TCS |
![]() March 2011 from 34 TCS |
![]() April 2011 from 32 MS |
![]() April 2011 from 32 MS |
![]() May 2011 from 34 TCS |
![]() May 2011 from 34 TCS |
![]() May 2011 from 32 MS |
![]() May 2011 from 32 MS |
![]() June 2011 from 32 MS |
![]() June 2011 from 32 MS |
![]() June 2011 from 32 MS |
![]() June 2011 from 32 MS |
18 May 2013 » Sign In